Comprehensive Primavera P6 Reports

Receive detailed insights on Primavera P6 schedule changes, critical path updates, and validate your logic in one clear report.

Secure & Simple

Enjoy a seamless sign‑up process and secure payments through Stripe. Your data is always safe and confidential.

Streamlined Reporting

Generate up to 50 detailed reports per month – an ideal balance for most projects, with custom options available on request.

Subscription Options

Enjoy a 14‑day commitment-free trial – cancel anytime.

*Each subscription includes up to 50 reports per month. For custom enterprise needs, please contact us.

Example Primavera P6 Schedule Comparison Report

Baseline update
Data Date July 25, 2024, 00:00 August 10, 2024, 00:00
Planned Start Date July 25, 2024, 00:00 July 25, 2024, 00:00
Must Finish By January 14, 2029, 16:00 January 28, 2029, 16:00
Scheduled Finish January 14, 2029, 16:00 June 24, 2029, 16:00

Critical Path Type: Changed from 'Longest Path' to 'Total Float Less Than Or Equal To'

Critical Duration Hour Count: Changed from '0' to '-24'

Activity ID Activity Name Primary Constraint Type Secondary Constraint Type
ACT-002 Complete Major Structural Work January 15, 2026, 16:00 Finish On or Before - -
ACT-003 Complete All Finishing Work January 31, 2029, 16:00 Finish On or Before - -
MILE-001 Begin Site Mobilization September 15, 2024, 08:00 Start On or Before - -
MILE-002 Complete West Side Work December 15, 2024, 16:00 Finish On or Before - -

Activity ID Activity Name Primary Constraint Type
ACT-003 Complete All Finishing Work January 31, 2029, 16:00 Finish On or Before

Activity ID Activity Name Primary Constraint Type
ACT-003 Complete East Side Work January 14, 2029, 16:00 Finish On or Before

Activity ID Activity Name Critical? Days Behind (CD) Baseline Early Start Date Baseline Early Finish Date Update Actual Start Date Update Actual Finish Date
SUB-1040 Submit Traffic Control Plan Critical 38 2024-07-25 08:00 2024-08-28 16:00 - -
SUB-1010 Submit Schedule of Values Not Critical 13 2024-07-25 08:00 2024-08-28 16:00 2024-09-01 08:00 -
SUB-1020 Submit Submittal Log Not Critical 23 2024-07-25 08:00 2024-08-28 16:00 - -

  • ACT-001: Start Construction
  • ACT-002: Complete Major Structural Work
  • ACT-003: Complete All Finishing Work
  • MILE-002: Complete West Side Work

  • ACT-001: Start Construction
  • GEN-1080: Contractor Starts Work/Mobilization
  • GEN-1030: Submit Safety Engineer
  • ACT-003: Complete All Finishing Work
  • ACT-004: Install Site Fencing and Guardrails
  • MILE-001: Begin Site Mobilization

Activity ID Activity Name Predecessor ID Relationship Note
GEN-1060 Review Project Engineer GEN-1050 Finish to Finish Finished at 2024-08-01 08:00 before predecessor finished at 2024-08-02 08:00 (FF)

Activity ID Activity Name Baseline Remaining Duration Update Remaining Duration Actual Start Date
GEN-1030 Submit Safety Engineer 1.0 1.0 2024-07-25 08:00
SUB-1030 Submit SWPPP 35.0 35.0 2024-07-25 08:00

  • GEN-1020: Review Insurance Requirements – Completed Predecessors: GEN-1010, SUB-1040, GEN-1000, MILE-0050

Activity ID Activity Name Calendar Type Original Duration
ACT-005 Install Earth Retention System 5 Day Workweek Task Dependent 0.0

Activity ID Activity Name Calendar Type Original Duration
PC-1000 Submit As-Built Drawings 5 Day Workweek Task Dependent 60.0
GEN-1040 Review Safety Engineer 5 Day Workweek Task Dependent 15.0

Activity ID Activity Name Baseline Activity ID Update Activity ID
REV-1020-1 Review Submittal Log REV-1020 REV-1020-1

Activity ID Baseline Name Update Name
SUB-1040 Submit Traffic Control Plan Submit Traffic Control Plan ABC Street

Activity ID Activity Name Baseline Calendar Update Calendar
ACT-003 Complete All Finishing Work 5 Day Workweek 7 Day Week

Activity ID Activity Name Baseline Type Update Type
GEN-1010 Establish Field Office Task Dependent Finish Milestone

Activity ID Activity Name Baseline Suspend Date Update Suspend Date
SUB-1020 Submit Submittal Log - 2024-08-05 08:00

Activity ID Activity Name Baseline Resume Date Update Resume Date
SUB-1020 Submit Submittal Log - 2024-08-16 08:00

Activity ID Activity Name Baseline Critical? Update Critical?
ELEC-1270 Install electrical control panel Critical Not Critical
CIV-3040 Final/Misc. grade, seed and blanket Critical Not Critical
STR-3020 Install caisson foundation, Area 2 Critical Not Critical
MECH-3000 Install RTU Building 2- Area 5 Critical Not Critical
ACT-006 Submit Financial Breakdown Critical Not Critical
CIV-1150 Fine Grade, Seed & Blanket Not Critical Critical
REV-1020-1 Review Submittal Log Critical Not Critical
ACT-007 Submit Project Documentation Log Critical Not Critical
CIV-1250 Construct Overlooks Critical Not Critical

Activity ID Activity Name Baseline Actual Start Update Actual Start
ACT-001 Start Construction 2024-07-25 08:00 -
GEN-1010 Submit Insurance Requirements 2024-07-25 08:00 2024-09-25 08:00
ACT-006 Submit Financial Breakdown 2024-08-01 08:00 2024-09-02 08:00
ACT-007 Submit Project Documentation Log 2024-08-01 08:00 2024-08-01 08:00

Warning: The following activities have Actual Start Dates after the data date (2024-08-10 00:00:00): GEN-1010, ACT-006

Activity ID Activity Name Baseline Actual Finish Update Actual Finish
ACT-001 Start Construction 2024-07-25 08:00 -
GEN-1010 Submit Insurance Requirements - 2024-09-26 16:00

Warning: The following activities have Actual Finish Dates after the data date (2024-08-10 00:00:00): GEN-1010

Activity ID Activity Name Baseline Original Duration Update Original Duration
SUB-1210 Submit Waste Management Plan 35.0 10.0
GEN-1010 Establish Field Office 7.0 0.0

Activity ID Activity Name Baseline Remaining Duration Update Remaining Duration
GEN-1010 Establish Field Office 7.0 0.0
GEN-1010 Submit Insurance Requirements 1.0 0.0
SUB-1210 Submit Waste Management Plan 35.0 10.0
ACT-006 Submit Financial Breakdown 35.0 10.0
ACT-007 Submit Project Documentation Log 35.0 20.0

Activity ID Activity Name Predecessor ID Predecessor Name Relationship Lag
A2050 Install Jacking & Receiving Pits ACT-005 Install Earth Retention System Finish to Start 0.0
ACT-005 Install Earth Retention System A2035 Locate Utilities Finish to Start 0.0

Activity ID Activity Name Predecessor ID Predecessor Name Relationship Lag
MILE-001 Begin Site Mobilization GEN-1040 Review Safety Engineer Finish to Start 0.0
GEN-1080 Contractor Starts Work/Mobilization GEN-1040 Review Safety Engineer Finish to Start 0.0
ACT-002 Complete Major Structural Work ACT-004 Install Site Fencing and Guardrails Finish to Finish 0.0
ACT-003 Complete All Finishing Work PC-1000 Submit As-Built Drawings Finish to Finish 0.0
GEN-1040 Review Safety Engineer GEN-1030 Submit Safety Engineer Finish to Start 0.0

Activity ID Activity Name Predecessor ID Predecessor Name Baseline Lag Update Lag
REV-1020 / REV-1020-1 Review Submittal Log ACT-007 Submit Project Documentation Log 0.0 10.0

Activity ID Activity Name Predecessor ID Baseline Relationship Update Relationship
GEN-1060 Review Project Engineer GEN-1050 Finish to Finish Finish to Finish

Calendar Name: 5 Day Work Week

Change Type: Calendar Added

Change Details: ADDED Workweek: Sunday: 08:00-16:00, Monday: 08:00-16:00, Tuesday: 08:00-16:00, Wednesday: 08:00-16:00, Thursday: 08:00-16:00, Friday: 08:00-16:00, Saturday: 08:00-16:00


Calendar Name: 7 Day Week

Change Type: Calendar Added

Change Details: ADDED Workweek: Sunday: 08:00-16:00, Monday: 08:00-16:00, Tuesday: 08:00-16:00, Wednesday: 08:00-16:00, Thursday: 08:00-16:00, Friday: 08:00-16:00, Saturday: 08:00-16:00


Calendar Name: Winter Shutdown 5 Day Work Week

Exceptions Changed: ADDED Exceptions – Exceptions that add working hours: 2025-04-15 (13:00-17:00), 2024-12-13 (08:00-16:00), 2024-12-20 (10:00-16:00); DELETED Exceptions – 2024-12-13, 2024-12-20 ([All Hours] removed)

Resource ID Resource Name Resource Type Unit of Measure Default Units/Time Calendar Name Status Units & Prices Roles
1234 Pipes Material Linear feet 8/d Trades - 5 Day Workweek Active Effective Date: 2025-01-01 00:00, Max Units/Time: 4/d, Standard Rate: $50.00/LF
Effective Date: 2025-03-03 00:00, Max Units/Time: 4/d, Standard Rate: $30.00/LF
Cleaner Cleaner Nonlabor 8/d Carpenters Shared 5x8 Active Effective Date: 2025-01-01 00:00, Max Units/Time: 8/d, Standard Rate: $0.00/hr Role ID: 1174, Role: Management, Proficiency: 3, Primary: N
Role ID: 1320, Role: Foreman, Proficiency: 3, Primary: N

Resource ID Resource Name Resource Type Unit of Measure Default Units/Time Calendar Name Status Units & Prices Roles
HVAC HVAC Labor Trades - 5 Day Workweek Active Effective Date: 2000-01-01 00:00, Max Units/Time: 16/d, Standard Rate: $44.00/hr Role ID: 1567, Role: Trades, Proficiency: 3, Primary: N

Resource ID Resource Name Field Changed resourcebase Value resourceupdate Value
E&C Resources E&C Resources Units & Prices Effective Date: 2010-01-01 00:00, Max Units/Time: 8/d, Standard Rate: $0.00/hr
Trades Trades Units & Prices Effective Date: 2010-01-01 00:00, Max Units/Time: 8/d, Standard Rate: $0.00/hr
Elec Electrician Roles Role ID: 1567, Role: Trades, Proficiency: 3, Primary: N Role ID: 1175, Role: Civil/Structural Crews, Proficiency: 3, Primary: N
Role ID: 1567, Role: Trades, Proficiency: 3, Primary: N
Floor Floor and Carpet Layer Units & Prices Effective Date: 2010-01-01 00:00, Max Units/Time: 24/d, Standard Rate: $45.00/hr Effective Date: 2010-01-01 00:00, Max Units/Time: 12/d, Standard Rate: $45.00/hr
Operator Operator status Active Inactive
Operator Operator Roles Role ID: 1567, Role: Trades, Proficiency: 3, Primary: N Role ID: 1175, Role: Civil/Structural Crews, Proficiency: 3, Primary: N
Role ID: 1567, Role: Trades, Proficiency: 3, Primary: N
GenLabor Laborer-Construction Roles Role ID: 1567, Role: Trades, Proficiency: 3, Primary: N Role ID: 1320, Role: Foreman, Proficiency: 3, Primary: N
Role ID: 1567, Role: Trades, Proficiency: 3, Primary: N
Exc Excavator Units & Prices Effective Date: 2010-01-01 00:00, Max Units/Time: 48/d, Standard Rate: $70.00/hr Effective Date: 2010-01-01 00:00, Max Units/Time: 24/d, Standard Rate: $55.00/hr
KimP Paul Kim resource_name Paul Kim Paul Jim
KimP Paul Kim Roles Role ID: 1174, Role: Management, Proficiency: 3, Primary: N Role ID: 1174, Role: Management, Proficiency: 2, Primary: N

Activity ID Activity Name Resource ID Resource Name Role Name Budgeted Units Remaining Units Primary Resource Start Date Finish Date Original Lag
EC1560 Install Door and Window Frames Paint Painter Trades 15.2 15.2 No
EC1420 Floor Decking 1234 Pipes 201.6 201.6 No
EC1080 Review and Approve Flooring Cleaner Cleaner Foreman 144 144 No

Activity ID Activity Name Resource ID Resource Name Role Name Budgeted Units Remaining Units Primary Resource Start Date Finish Date Original Lag
EC1630 Insulate Ducts HVAC HVAC Civil/Structural Crews 28.8 28.8 No
EC1500 Install HVAC Ducts HVAC HVAC Civil/Structural Crews 144 144 No
EC1820 Touch-up and Clean-up Paint Painter Civil/Structural Crews 4.8 4.8 No
EC1850 Punch List FCarp Finish Carpenter Civil/Structural Crews 28.8 28.8 No
EC1670 Relocate HVAC Chiller HVAC HVAC Civil/Structural Crews 43.2 43.2 No

Activity ID Activity Name Resource ID Resource Name Field Changed resourcebase Value resourceupdate Value
EC1850 Punch List GenLabor Laborer-Construction Budgeted Units 28.8 10
EC1850 Punch List GenLabor Laborer-Construction Remaining Units 28.8 5
EC1850 Punch List GenLabor Laborer-Construction Start Date 2013-10-14 08:00
EC1850 Punch List Paint Painter Role Name Civil/Structural Crews Foreman
EC1850 Punch List Paint Painter Start Date 2013-10-14 08:00
EC1560 Install Door and Window Frames FCarp Finish Carpenter Role Name Civil/Structural Crews Electrical Engineer

Activity ID Activity Name Expense Item Expense Category Budgeted Units Price/Unit Budgeted Cost Remaining Cost Vendor Auto Compute Actuals
EC1550 Brick Exterior Walls Backhoe 478 $800.00 $1,600.00 $1,600.00 N
EC1560 Install Door and Window Frames (New Expense Item) 11 $0.00 $0.00 $0.00 123 llc N
EC1560 Install Door and Window Frames Hinges shipping 22 $0.00 $0.00 $0.00 abc co. N

Activity ID Activity Name Expense Item Expense Category Budgeted Units Price/Unit Budgeted Cost Remaining Cost Vendor Auto Compute Actuals
EC1600 Insulation and Built-up Roofing Crane 478 $800.00 $800.00 $800.00 N

Activity ID Activity Name Expense Item Field Changed resourcebase Value resourceupdate Value
EC1550 Brick Exterior Walls Crane Price/Unit $2,240.00 $2,040.00
EC1550 Brick Exterior Walls Crane Budgeted Cost $6,720.00 $2,040.00
EC1550 Brick Exterior Walls Crane Remaining Cost $6,720.00 $1,540.00

Categories With No Changes Between Baseline and Update / Categories With No Items to Report:

  • WBS or Parent WBS

The full report above illustrates every detailed change detected between baseline and update, providing actionable insights for effective project management.