Comprehensive Glossary of CPM & P6 Scheduling Terms
A detailed reference of key scheduling terms for project management professionals using CPM and Primavera P6, including .xer file handling and delay analysis concepts.
General Terms
- Activity: A task or set of tasks required to complete a project.
- Activity Code: Labels used to sort, filter, and organize schedule activities.
- Milestone: A significant point or event in the project timeline with zero duration.
- Work Breakdown Structure (WBS): Hierarchical decomposition of project scope into manageable components.
Schedule Structure
- Baseline: The original approved project schedule, used as a reference for tracking progress.
- Baseline Schedule: The approved project schedule frozen for tracking changes over time.
- Baseline Type: Classification of baseline versions (e.g., primary, secondary).
- Calendar: Defines working and non-working time periods for the project and resources.
- Data Date: The current date being used for schedule updates and progress reporting.
- Time-Scaled Logic Diagram: Network diagram showing activities on a time scale.
Scheduling Concepts
- Concurrent Activities: Two or more activities scheduled to occur simultaneously.
- Critical Path: The longest sequence of tasks determining the shortest time to complete a project.
- Duration, Actual: The elapsed time from when an activity started to when it finished, measured in working days.
- Duration, Original: The estimated number of working days required to complete an activity, excluding holidays. This duration is determined by the assigned activity calendar.
- Duration, Remaining: The number of working days needed to complete an activity as of the data date.
- Early Start/Finish: Earliest dates an activity can begin/end based on network logic.
- Float, Free (FF): Time an activity can be delayed without affecting successor activities.
- Float, Total (TF): Time an activity can be delayed without extending the project completion date.
- Gantt Chart: A bar chart used to visualize a project schedule. Each bar represents an activity, with its length proportional to the activity's duration. Often includes dependencies between activities.
- Late Start/Finish: Latest dates an activity can begin/end without delaying the project.
Schedule Compression
- Crashing: Adding resources to compress the schedule duration at minimal cost increase.
- Fast Track: Scheduling technique where activities are performed in parallel rather than sequentially to compress duration.
- Schedule Compression: Techniques to reduce project duration without changing scope (e.g., crashing, fast tracking).
Resource Management
- Cost Loading: Assigning costs to schedule activities to create time-phased budgets.
- Resource Loading: Assigning labor, equipment, and materials to schedule activities.
- Resource Optimization: Adjusting resource allocations to avoid conflicts or overallocations.
Dependencies and Relationships
- Dependencies: Logical relationships between activities, such as finish-to-start or start-to-start links.
- Lead: An overlap where a successor activity starts before its predecessor finishes.
- Lag: A delay applied to a dependency between two activities.
- Predecessor: An activity that must be completed before another activity can begin.
- Successor: An activity that follows and depends on the completion of another activity.
Risk and Analysis
- Buffer/Contingency: Reserved time added to activities or the overall schedule to account for uncertainty and risk.
- Half-Step or Bifurcation Schedule Analysis: A technique that separates the effects of schedule changes and activity progress.
- Out-of-Sequence Progress: Work performed in a different order than planned logic.
- Progress Override: Schedule calculation option for handling out-of-sequence work.
- Retained Logic: Schedule calculation option maintaining planned activity sequences.
- Schedule Network Analysis: Techniques to identify early dates, late dates, and float using forward and backward pass calculations.
- Schedule Risk Analysis: Monte Carlo simulation to assess schedule uncertainty.
- Variance Analysis: The process of comparing planned performance to actual performance to identify deviations.
Support Activities
- Level of Effort (LOE): Support activities, like project management, that continue for the project duration.
Visualization Tools
- Gantt Chart: A bar chart used to visualize a project schedule. Each bar represents an activity, with its length proportional to the activity's duration. Often includes dependencies between activities.