Comprehensive Glossary of CPM & P6 Scheduling Terms

A detailed reference of key scheduling terms for project management professionals using CPM and Primavera P6, including .xer file handling and delay analysis concepts.

General Terms

  • Activity: A task or set of tasks required to complete a project.
  • Activity Code: Labels used to sort, filter, and organize schedule activities.
  • Milestone: A significant point or event in the project timeline with zero duration.
  • Work Breakdown Structure (WBS): Hierarchical decomposition of project scope into manageable components.

Schedule Structure

  • Baseline: The original approved project schedule, used as a reference for tracking progress.
  • Baseline Schedule: The approved project schedule frozen for tracking changes over time.
  • Baseline Type: Classification of baseline versions (e.g., primary, secondary).
  • Calendar: Defines working and non-working time periods for the project and resources.
  • Data Date: The current date being used for schedule updates and progress reporting.
  • Time-Scaled Logic Diagram: Network diagram showing activities on a time scale.

Scheduling Concepts

  • Concurrent Activities: Two or more activities scheduled to occur simultaneously.
  • Critical Path: The longest sequence of tasks determining the shortest time to complete a project.
  • Duration, Actual: The elapsed time from when an activity started to when it finished, measured in working days.
  • Duration, Original: The estimated number of working days required to complete an activity, excluding holidays. This duration is determined by the assigned activity calendar.
  • Duration, Remaining: The number of working days needed to complete an activity as of the data date.
  • Early Start/Finish: Earliest dates an activity can begin/end based on network logic.
  • Float, Free (FF): Time an activity can be delayed without affecting successor activities.
  • Float, Total (TF): Time an activity can be delayed without extending the project completion date.
  • Gantt Chart: A bar chart used to visualize a project schedule. Each bar represents an activity, with its length proportional to the activity's duration. Often includes dependencies between activities.
  • Late Start/Finish: Latest dates an activity can begin/end without delaying the project.

Schedule Compression

  • Crashing: Adding resources to compress the schedule duration at minimal cost increase.
  • Fast Track: Scheduling technique where activities are performed in parallel rather than sequentially to compress duration.
  • Schedule Compression: Techniques to reduce project duration without changing scope (e.g., crashing, fast tracking).

Resource Management

  • Cost Loading: Assigning costs to schedule activities to create time-phased budgets.
  • Resource Loading: Assigning labor, equipment, and materials to schedule activities.
  • Resource Optimization: Adjusting resource allocations to avoid conflicts or overallocations.

Dependencies and Relationships

  • Dependencies: Logical relationships between activities, such as finish-to-start or start-to-start links.
  • Lead: An overlap where a successor activity starts before its predecessor finishes.
  • Lag: A delay applied to a dependency between two activities.
  • Predecessor: An activity that must be completed before another activity can begin.
  • Successor: An activity that follows and depends on the completion of another activity.

Risk and Analysis

  • Buffer/Contingency: Reserved time added to activities or the overall schedule to account for uncertainty and risk.
  • Half-Step or Bifurcation Schedule Analysis: A technique that separates the effects of schedule changes and activity progress.
  • Out-of-Sequence Progress: Work performed in a different order than planned logic.
  • Progress Override: Schedule calculation option for handling out-of-sequence work.
  • Retained Logic: Schedule calculation option maintaining planned activity sequences.
  • Schedule Network Analysis: Techniques to identify early dates, late dates, and float using forward and backward pass calculations.
  • Schedule Risk Analysis: Monte Carlo simulation to assess schedule uncertainty.
  • Variance Analysis: The process of comparing planned performance to actual performance to identify deviations.

Support Activities

  • Level of Effort (LOE): Support activities, like project management, that continue for the project duration.

Visualization Tools

  • Gantt Chart: A bar chart used to visualize a project schedule. Each bar represents an activity, with its length proportional to the activity's duration. Often includes dependencies between activities.